Base, Risk, Range, Select, Control. Runs offline in your browser. Your data stays on this computer.
1. Base Estimate
Enter each line in $ thousands (excl. GST, excl. escalation). Tag the confidence: Measured, Allowed or Assumed.
| Line item | Tag | Min | Most likely | Max | Spread vs likely |
|---|
0Base (sum of most likely)
0Expected total (three-point)
Tip: wider ranges for Allowed and Assumed lines. Keep contingency out of the rates.
2. Risk Register
One specific risk per row (cause, event, effect). Probability in %, impact in $ thousands.
| Risk statement | Owner | Prob % | Min | Most likely | Max | Expected value | Response / trigger |
|---|
0Total expected value of events ($k)
3. Range and Select
Three-point hand method and a simulation of line ranges plus risk events.
Record who chose the confidence level, when, and why:
4. Budget Stack and Allocation
Uses the simulated total at your chosen confidence. Run the simulation first.
5. Drawdown Log and Cover Ratio
Every draw links to a risk or a documented reason. Variations are not contingency draws.
| Date | Amount $k | Linked risk / reason | Bucket | Approved by | Balance $k |
|---|
6. One-Page Contingency Report
Print or save as PDF from your browser.